North Creek Trail Section 4

News & project updates


March 8, 2017


Muriel's Landing residents came to a public meeting on Mar. 2 to learn about the project and ask questions. Here are the materials we presented and the meeting summary.

About the project


North Creek Trail Section 4 is the last missing segment of the North Creek Trail within Bothell’s city limits. It will consist of a 10-foot wide shared use path along Filbert Road (SR 524). It will connect the planned Snohomish County North Creek Trail north of the SR 524 with the nearly completed North Creek Trail Section 3 in Bothell. Completion of this missing segment will result in a continous trail connecting to the Sammamish River/Burke Gilman Trail in King County and the Interurban Trail at McCollum Park in Snohomish County.

Proposed trail alignment for Section 4 (click to enlarge)

Proposed alignment for North Creek Trail Section 4, aerial view (JPG)

Funding


In 2014, the City received a $735,000 CMAQ Federal grant for the design of North Creek Trail Section 4. In 2016, we received an STP Federal grant for $1,015,800 to complete right-of-way acquisition for Section 4.

Anticipated schedule


October 2016

– Begin trail design

2018

– Complete trail design/environmental documentation

2019

– Begin-right-of way acquisition process

2020

– Complete right-of-way acquisition/certification

Early 2021

– Begin construction

Spring 2022

– Complete construction