Beardslee Blvd Paving Traffic Alerts

Weekly traffic update

DatesDaysLocationTraffic impactTimes
6/25-29/18Mon - FriBeardslee Blvd from Sunrise Dr to 110th Ave NEPeriodic one-way closures9 a.m. - 3 p.m.
6/19 - mid-August7 days/weekBeardlsee Blvd from NE 185th St. to 110th Ave NEWestbound closure24 hours/day

Westbound closure of Beardslee Boulevard 

Summer 2018

Beardslee Boulevard is closed to westbound traffic through mid-August, weather permitting. The work will include:

  • asphalt pavement overlay (paving) from Sunrise Drive to NE 185th St., and
  • pavement reconstruction from NE 185th St. to 110th Ave NE. 

Traffic impacts

  • Westbound Beardslee Boulevard will be closed.
  • A detour will be in place for westbound drivers, see map below.
  • Eastbound drivers can expect some delays.
  • No street parking will be available within the affected areas.

This work is part of the Beardslee Blvd. Paving Overlay project, which makes up a portion of the City's Safe Streets and Sidewalks levy-funded Pavement Preservation Program.

Map of closure and detour

Beardslee Blvd Closure