19th Ave. SE Storm System Improvements

This project will remove a damaged culvert underneath an access road near 19th Ave. SE, and extend and realign the Perry Creek stream channel for approximately 200 linear ft. It will also relocate the pond access road, and restore the repair areas with native vegetation.

Schedule

Construction is anticipated to begin in July 2019 and estimated to be completed by fall of 2019.

Map

19thAveSEStormVicinityMap