About the Project

The Washington State Department of Transportation (WSDOT), with its planned I405 Express toll Lane project, proposes to impact the existing PW Shop 1 building and require its demolition.  To mitigate this, WSDOT has agreed to fund the demolition and replacement of a new, comparable shop.   Shop 1 is anticipated to include large-equipment bays, restroom, break area and relocation of the existing back-up electric generator.  The current shop is approximately 6,650  square feet in site.

Schedule

TimelineWhat's Happening

Summer 2022                        

Existing Building Demolition/Preliminary Studies for New Building
Fall 2022                       Begin Design
Fall 2023 Begin Construction